King’s Mill Hospital, UK

The King's Mill Hospital project involved installing an array of SJ-10T (304SS) Slim Jim® plates to create 1,400 Ton exchanger system.

PROJECT OVERVIEW

Kings Mill Hospital in Nottinghamshire, UK, which provides healthcare for 300,000 people, underwent a major redevelopment.

Part of the renovation was the installation of a geothermal heat pump system specifically deployed to reduce environmental impact and save money.

A 1,400 ton lake-source heat pump cooling and heating system that is capable of producing 5.4MW of cooling and 5MW of heating was installed.

A network of heat exchangers submerged in the adjacent Kings Mill Reservoir is connected to 42 heat pumps in the hospital, which regulate the temperature. The system is the largest geothermal lake loop in Europe and will fulfill the hospital’s entire needs for cooling and support the gas heating system when the capacity is available, annually saving 9,600 MWh of gas and electricity.

Skanska consulted local preservation and wildlife groups and the heat exchangers were installed during the winter to minimize disturbance. A floating reed bed has been added to conceal and protect the exchangers and to create new habitats for wildlife.

Read More About the King's Mill Hospital Project

Key Facts

  • Closed Lake Loop System
  • 5,400 kW Cooling, 5,000 kW Heating
  • 4 Hour Response Maintenance
  • 25,000 Gj Saved per Year
  • 2,078 tons of Carbon Saved per Year
  • Cost Savings around £126,500 per Year

PROJECT IMAGE GALLERY

    Please select the model of the sizing requested

    You will receive the following attachments in an email for your information:

    • Installation Requirements Info Sheet

    • Project Information Sheet – (For Slim Jim® and Geo Lake Plate® Exchanger Sizing, please complete this document and return to AWEB Supply)

    • Slim Jim® Geo Lake Plate Packet

    • Additional Details of Your Project